Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
02 Dec 2024 | Completed on 30/11/2024 | Perlassery Sn 2 AE | |
02 Dec 2024 | 5165m pipe laid.224nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE) | Perlassery Sn 2 AE | |
27 Nov 2024 | 5165m pipe laid.215nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE) | Perlassery Sn 2 AE | |
23 Nov 2024 | 5165m pipe laid.210nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE) | Perlassery Sn 2 AE | |
18 Nov 2024 | 5165m pipe laid.201nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE) | Perlassery Sn 2 AE | |
12 Nov 2024 | 5165m pipe laid.173nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE) | Perlassery Sn 2 AE | |
06 Nov 2024 | 5165m pipe laid.137nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE) | Perlassery Sn 2 AE | |
02 Nov 2024 | 5165m pipe laid.137nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE) | Perlassery Sn 2 AE | |
25 Oct 2024 | 5165m pipe laid.121nos. FHTC provided ( proposed 50 FHTCs , excess quantity executed based on approved RE) | Perlassery Sn 2 AE | |
25 Oct 2024 | 95% work completed.5165m pipe laid.109 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE |