Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
19 Oct 2024 | 95% work completed.5165m pipe laid.109 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
15 Oct 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
08 Oct 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
08 Oct 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
04 Oct 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
30 Sep 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
23 Sep 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
18 Sep 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
09 Sep 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE | |
04 Sep 2024 | 95% work completed.5165m pipe laid.61 Nos.FHTC Provided. Part bill submitted | Perlassery Sn 2 AE |