Sl.No. | Component | Description |
---|---|---|
1 | Supply and laying of transmission main 1A1 - Thalavady, Edathua, Veeyapuram. | 500 mm HDPE pipe- 3030m, 250 mm DI pipe -180m,400 mm HDPE pipe- 2460m, 180 mm HDPE pipe- 550 m |
2 | Construction of OHSR at Thalavady, Edathua, Veeyapuram and rehabilitation of existing OHSR at Veeyapuram and Thalavady. | OHSR at Thalavadi - 8 LL, OHSR at Edathuva - 11 LL, OHSR at Veeyapuram - 4.75 LL |
3 | Construction of Staff Quarters, Office building at Neerattupuram and Edathuva |