Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
10 Feb 2022 Scheme Commissioned, Pumping Started, Road Restoration Work Started Except BM/BC Work, Bitumen emulsions supplied by contractor phase -II 98% completed Palakkad Project Dn AE
09 Feb 2022 Scheme Commissioned, Pumping Started, Road Restoration Work Started Except BM/BC Work, Bitumen emulsions supplied by contractor phase -II 98% completed Palakkad Project Dn AE
08 Feb 2022 Scheme Commissioned, Pumping Started, Road Restoration Work Started Except BM/BC Work, Bitumen emulsions supplied by contractor phase -II 98% completed Palakkad Project Dn AE
20 Dec 2021 Scheme commissioned Palakkad Project Dn AE
24 Sep 2021 All works completed , energisation, trial running and road restoration works are to be completed Palakkad Project Dn AE
18 Apr 2021 WTP major RCC works completed, filter house brick works completed, plastering 70% completed, chemical house plastering completed, flash mixer RCC works completed, aerator RCC works completed, clarifier bridge mechanical works completed, pipe gallery works ongoing. Clear water Pumping main works completed. OHSR works completed Palakkad Project Dn AE
21 Mar 2021 WTP major RCC works completed, filter house brick works ongoing, chemical house plastering finishing stage, flash mixer 60% completed, aerator 50%completed, clarifier bridge mechanical works completed, pipe gallery works ongoing. Clear water Pumping main works completed Palakkad Project Dn AE
12 Mar 2021 Phase 1 completed, phase 2 - WTP -major structural works completed, mechanical works going on, OHSR -works completed except painting. Palakkad Project Dn AE
26 Jan 2021 Phase II 70%completed Palakkad Project Dn AE
26 Jan 2021 Phase II 75% completed Palakkad Project Dn AE