Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
10 Feb 2022 | Scheme Commissioned, Pumping Started, Road Restoration Work Started Except BM/BC Work, Bitumen emulsions supplied by contractor phase -II 98% completed | Palakkad Project Dn AE | |
09 Feb 2022 | Scheme Commissioned, Pumping Started, Road Restoration Work Started Except BM/BC Work, Bitumen emulsions supplied by contractor phase -II 98% completed | Palakkad Project Dn AE | |
08 Feb 2022 | Scheme Commissioned, Pumping Started, Road Restoration Work Started Except BM/BC Work, Bitumen emulsions supplied by contractor phase -II 98% completed | Palakkad Project Dn AE | |
20 Dec 2021 | Scheme commissioned | Palakkad Project Dn AE | |
24 Sep 2021 | All works completed , energisation, trial running and road restoration works are to be completed | Palakkad Project Dn AE | |
18 Apr 2021 | WTP major RCC works completed, filter house brick works completed, plastering 70% completed, chemical house plastering completed, flash mixer RCC works completed, aerator RCC works completed, clarifier bridge mechanical works completed, pipe gallery works ongoing. Clear water Pumping main works completed. OHSR works completed | Palakkad Project Dn AE | |
21 Mar 2021 | WTP major RCC works completed, filter house brick works ongoing, chemical house plastering finishing stage, flash mixer 60% completed, aerator 50%completed, clarifier bridge mechanical works completed, pipe gallery works ongoing. Clear water Pumping main works completed | Palakkad Project Dn AE | |
12 Mar 2021 | Phase 1 completed, phase 2 - WTP -major structural works completed, mechanical works going on, OHSR -works completed except painting. | Palakkad Project Dn AE | |
26 Jan 2021 | Phase II 70%completed | Palakkad Project Dn AE | |
26 Jan 2021 | Phase II 75% completed | Palakkad Project Dn AE |