| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Mar 2024 | Work in progress | Punalur WS Sn - AE | |
| 19 Mar 2024 | work in progress | Punalur WS Sn - AE | |
| 15 Mar 2024 | Work In Progress | Punalur WS Sn - AE | |
| 28 Feb 2024 | Work in progress | Punalur WS Sn - AE | |
| 22 Feb 2024 | On going | Punalur WS Sn - AE | |
| 14 Feb 2024 | Pipe laying works started. | Kottarakkara PH Dn EE | |
| 22 May 2023 | Retendered. Extended to 23.05.2023 | Kottarakkara PH Dn EE | |
| 15 May 2023 | Work tendered on with opening dt 22-4-23. No offer recieved. To be re-tendered | Punalur WS Sn - AE | |
| 11 May 2023 | Work tendered on with opening dt 22-4-23. No offer recieved. To be re-tendered | Punalur WS Sn - AE | |
| 08 May 2023 | Work tendered on with opening dt 22-4-23. No offer recieved. To be re-tendered | Punalur WS Sn - AE |