| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 29 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 25 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 23 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 19 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 16 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 14 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 11 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 08 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 07 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE | |
| 05 Sep 2023 | AS,TS issued. TEndering under process in circle office. due date 12.06.23 opening date 13.06.23 | Oachira AE |