Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
10 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
09 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
08 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
07 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
06 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
05 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
04 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
03 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE | |
02 Dec 2023 | work completed bill submitted | Kaduthuruthy Dn EE |