| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Sep 2021 | providing FHTC in ward1,10,11 | Kaduthuruthy Dn EE | |
| 16 Sep 2021 | No work due to heavy rain | Kaduthuruthy Dn EE | |
| 15 Sep 2021 | providing FHTC in ward1,10,11 | Kaduthuruthy Dn EE | |
| 14 Sep 2021 | FHTC-1464Nos 160 mm pvc-400m 110 mm pvc-700m 90 mm pvc-10000m 80 mm GI-300m 20 mm pvc-24417m | Kaduthuruthy Dn EE | |
| 14 Sep 2021 | providing FHTC in ward 10,11 | Kaduthuruthy Dn EE | |
| 13 Sep 2021 | Work nil due to heavy rain | Kaduthuruthy Dn EE | |
| 12 Sep 2021 | providing FHTC in ward 1 | Kaduthuruthy Dn EE | |
| 11 Sep 2021 | providing FHTC | Kaduthuruthy Dn EE | |
| 10 Sep 2021 | Pipe laying and providing FHTC in ward 3,4,13 | Kaduthuruthy Dn EE | |
| 09 Sep 2021 | Pipe laying and providing FHTC in ward 2,4,13 | Kaduthuruthy Dn EE |