| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Mar 2021 | Work completed | Aruvikkara HW Dn EE | |
| 11 Mar 2021 | Work completed | Aruvikkara HW Dn EE | |
| 04 Mar 2021 | Work completed | Aruvikkara HW Dn EE | |
| 03 Mar 2021 | work on going | Aruvikkara HW Dn EE | |
| 25 Feb 2021 | 600 FHTCs completed and bill for 481 FHTCs submitted and balance bill for 119 FHTCs prepared and will submitted on 26.02.2021. | Aruvikkara HW Dn EE | |
| 14 Feb 2021 | work completed. | Aruvikkara HW Dn EE | |
| 10 Feb 2021 | Road concreting, Fixing of GM Valves and air valve going on. | Aruvikkara HW Dn EE | |
| 09 Feb 2021 | Road concreting, Fixing of GM Valves and air valve going on. | Aruvikkara HW Dn EE | |
| 26 Jan 2021 | Work completed on 25.01.2021( 600 FHTCs) and bill for 481 FHTCs submitted and 239 FHTCs paid. | Aruvikkara HW Dn EE | |
| 19 Dec 2020 | 320 connections out of 600 given | Aruvikkara HW Dn EE |