Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Jun 2021 Estimate recasted and submitted Pattoor Sewerage Dn
31 May 2021 Alternate route estimate is under preparation. Pattoor Sewerage Dn
28 May 2021 Alternate route estimate is under preparation. Pattoor Sewerage Dn
23 May 2021 Alternate route estimate is under preparation. Pattoor Sewerage Dn
17 May 2021 Alternate route estimate is under preparation. Pattoor Sewerage Dn
12 May 2021 Alternate route estimate is under preparation. Pattoor Sewerage Dn
07 May 2021 Alternate route estimate is under preparation. Pattoor Sewerage Dn
03 May 2021 Alternate route estimate is under preparation. Pattoor Sewerage Dn
28 Apr 2021 Alternate route estimate is under preparation. Pattoor Sewerage Dn
26 Apr 2021 For alternate route recasting of estimate , survey work completed and level sheet prepararion ongoing Pattoor Sewerage Dn