Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Dec 2023 Cooling pipe line work completed .cooling pump started Valakom Sub Dn AEE
07 Dec 2023 Cooling pipe line work completed .cooling pump started Valakom Sub Dn AEE
04 Dec 2023 Cooling pipe line work completed .cooling pump started Valakom Sub Dn AEE
30 Nov 2023 Cooling pipe line work completed .cooling pump started Valakom Sub Dn AEE
27 Nov 2023 cooling pump purchased departmentally. Valakom Sub Dn AEE
22 Nov 2023 cooling pump purchased departmentally. Valakom Sub Dn AEE
20 Nov 2023 cooling pump purchased departmentally. Valakom Sub Dn AEE
17 Nov 2023 cooling pump purchased departmentally. Valakom Sub Dn AEE
15 Nov 2023 cooling pump purchased departmentally. Valakom Sub Dn AEE
13 Nov 2023 Work tendered 3 times. No offer received. Requested for departmental execution. Supply order given for custom made pumpset Valakom Sub Dn AEE