Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Oct 2022 | 31% work completed | Kattapana AE 1 | |
21 Oct 2022 | 31% work completed. | Kattappana AEE 1 | |
18 Oct 2022 | 31% WORK COMPLETED. | Kattapana AE 1 | |
15 Oct 2022 | 31% WORK COMPLETED. | Kattapana AE 1 | |
30 Mar 2022 | 360 FHTC given and bill submitted. Road restoration work in progress.More connections can be given only after commisioning of the scheme CARWSS to Kattappana and Kanjiyar Villages | Kattapana AE 1 | |
03 Nov 2021 | 26%work completed.209 fhtc given. | Kattappana AEE 1 | |
21 Oct 2021 | 18% work completed | Kattappana Project Dn EE | |
17 Sep 2021 | 32 Nos 80mm GI pipe laid till 16/9/21 | Kattappana AEE 1 | |
08 Sep 2021 | Agreement executed on 9/08/2021, Agreement number 3/2021-22/SE/PHC/MVPA. Material supplied. | Kattappana AEE 1 | |
03 Sep 2021 | Supply of materials in progress | Kattappana AEE 1 |