10 Aug 2022 | Work in progress | Kattapana Project Dn AE4 | |
01 Jun 2022 | Work in progress | Kattapana Project Dn AE4 | |
12 May 2022 | Work in progress | Kattapana Project Dn AE4 | |
10 May 2022 | Work in progress | Kattapana Project Dn AE4 | |
20 Apr 2022 | Laying distribution under progress | Kattapana Project Dn AE4 | |
18 Apr 2022 | Providing FHTC under progress | Kattapana Project Dn AE4 | |
01 Apr 2022 | providing FHTC under progress. | Kattapana Project Dn AE4 | |
25 Mar 2022 | Laying of distribution under progress. | Kattapana Project Dn AE4 | |
21 Mar 2022 | Work Started. Laying pipe in progress | Kattapana Project Dn AE4 | |
02 Feb 2022 | Agreement Executed on 6.1.22 | Kattapana Project Dn AE4 |