10 Mar 2024 Work completed. Bill Submitted. Shoranur PH Sn AE
02 Mar 2024 Submitted Shoranur PH Sn AE
25 Feb 2024 Work completed. Bill Submitted. Shoranur PH Sn AE
19 Feb 2024 Work completed. Bill Submitted. Shoranur PH Sn AE
12 Feb 2024 Work completed. Bill Submitted. Shoranur PH Sn AE
08 Feb 2024 Work completed. Bill submitted Shoranur PH Sn AE
29 Jan 2024 Work completed. Bill submitted Shoranur PH Sn AE
29 Jan 2024 Work completed. Bill submitted. Shoranur PH Sn AE
16 Aug 2023 18000 M OF PE 90MM ,4000 M OF PE 110M LAID,3000 M GI PIPE LAID, 170FHTCS, Road Restoration Concrete work completed,tarring work completed Shornur PH Dn EE