| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Apr 2026 | 2.5 km pipe line laid | Keezhallur PH Sn AE | |
| 08 Apr 2026 | 2.1 km pipe line laid | Keezhallur PH Sn AE | |
| 30 Mar 2026 | Pipe line laid 1.2 km | Keezhallur PH Sn AE | |
| 26 Mar 2026 | Work started | Keezhallur PH Sn AE | |
| 11 Mar 2026 | Work order issued. | Koothuparambu PH Sn AE | |
| 02 Mar 2026 | Work order issued. | Koothuparambu PH Sn AE | |
| 17 Feb 2026 | Work order issued. | Kannur PH Dn EE | |
| 02 Feb 2026 | Work order issued. | Kannur PH Dn EE | |
| 22 Jan 2026 | Tender under scrutiny. | Kannur PH Dn EE | |
| 08 Jan 2026 | Tender under scrutiny. | Koothuparambu PH Sn AE |