Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
23 Jan 2024 | 1000HTC connection completed | Tirurangadi AE | |
23 Dec 2023 | 1000HTC connection completed | Tirurangadi AE | |
19 Dec 2023 | 1000HTC connection completed | Tirurangadi AE | |
24 Nov 2023 | 800HTC connection completed | Tirurangadi AE | |
15 Nov 2023 | 35 km pvc pipe laid | Tirurangadi AE | |
15 Nov 2023 | 30km pvc pipe laid | Tirurangadi AE | |
07 Nov 2023 | 31km pvc pipe laid | Tirurangadi AE | |
28 Oct 2023 | 30km pvc pipe laid | Tirurangadi AE | |
18 Oct 2023 | 25 km pvc pipe laid | Malappuram PH Dn EE | |
09 Mar 2023 | Agreement Executed on 09/03/2023 | Malappuram PH Dn EE |