| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Jun 2022 | pipe supplied | Painavu PH Section AE | |
| 20 Jun 2022 | Agreement executed on pipe test procedures | Painavu PH Section AE | |
| 16 Jun 2022 | Agreement executed on pipe test procedures | Painavu PH Section AE | |
| 13 Jun 2022 | Agreement executed on pipe test procedures | Painavu PH Section AE | |
| 04 Jun 2022 | Agreement executed on pipe test procedures | Painavu PH Section AE | |
| 31 May 2022 | Agreement executed on pipe test procedures | Thodupuzha PH Dn EE | |
| 28 May 2022 | Agreement execute | Painavu PH Section AE | |
| 23 May 2022 | Agreement executed | Thodupuzha PH Dn EE | |
| 19 May 2022 | Agreement executed | Painavu PH Section AE | |
| 16 May 2022 | Agreement executed | Painavu PH Section AE |