| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Mar 2025 | bill submitted | Kottarakkara PH Sn - AE | |
| 26 Mar 2025 | Bill Completed and submitted | Kottarakkara PH Sn - AE | |
| 22 Mar 2025 | Laying completed with end cap | Kottarakkara PH Sn - AE | |
| 20 Mar 2025 | Laying | Kottarakkara PH Sn - AE | |
| 15 Mar 2025 | 50mm Pvc Line Laying | Kottarakkara PH Sn - AE | |
| 10 Mar 2025 | 50mm Pvc Laying | Kottarakkara PH Sn - AE | |
| 08 Mar 2025 | 75mm Pvc pipe laying completed | Kottarakkara PH Sn - AE | |
| 04 Mar 2025 | 75mm Pvc Line Laying | Kottarakkara PH Sn - AE | |
| 28 Feb 2025 | Earth Work | Kottarakkara PH Sn - AE | |
| 25 Feb 2025 | Earth Work | Kottarakkara PH Sn - AE |