| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Dec 2024 | Pipe Supplied and awaiting DN from PWD | Oachira AE | |
| 12 Dec 2024 | Pipe Supplied and awaiting DN from PWD | Oachira AE | |
| 11 Dec 2024 | Pipe Supplied and awaiting DN from PWD | Oachira AE | |
| 10 Dec 2024 | Pipe Supplied and awaiting DN from PWD | Oachira AE | |
| 09 Dec 2024 | Pipe Supplied and awaiting DN from PWD | Oachira AE | |
| 07 Dec 2024 | Pipe Supplied and awaiting DN from PWD | Oachira AE | |
| 05 Dec 2024 | Pipe Supplied and awaiting DN from PWD | Oachira AE | |
| 02 Dec 2024 | Pipe Supplied and awaiting DN from PWD | Oachira AE | |
| 28 Nov 2024 | Pipe Supplied and waiting sanction from PWD | Oachira AE | |
| 25 Nov 2024 | Pipe Supplied and waiting sanction from PWD | Oachira AE |