Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Mar 2024 | Work completed | Shoranur PH Sn AE | |
10 Mar 2024 | refurbishing the Filter Beds 2 nos completed ,1 filter bed work ongoing, | Shoranur PH Sn AE | |
02 Mar 2024 | refurbishing the Filter Beds 2 nos completed ,1 filter bed work ongoing, | Shoranur PH Sn AE | |
25 Feb 2024 | refurbishing the Filter Beds 2 nos completed ,1 filter bed work ongoing | Shoranur PH Sn AE | |
19 Feb 2024 | Anthracite is supplied, refurbishing the Filter Beds ongoing, Road concrete Completed. | Shoranur PH Sn AE | |
12 Feb 2024 | Anthracite is supplied, refurbishing the Filter Beds ongoing, Road concrete Completed. | Shoranur PH Sn AE | |
08 Feb 2024 | Anthracite is supplied, refurbishing the Filter Beds ongoing, Road concrete Completed. | Shoranur PH Sn AE | |
29 Jan 2024 | Anthracite is supplied, refurbishing the Filter Beds ongoing, Road concrete Completed. | Shoranur PH Sn AE | |
27 Dec 2022 | 90mm PE pipe laid 6500 M,110mm PEpipe 3500m,20 fhtcs | Shornur PH Dn EE | |
09 Oct 2022 | 90mm PE pipe laid 1600m | Shoranur PH Sn AE |