| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Oct 2024 | FENCING COMPLETED...ONLY PAINTING WORK REMAINING | Thaliparamba WS Dn EE | |
| 28 Oct 2024 | FENCING COMPLETED...ONLY PAINTING WORK REMAINING | Thaliparamba WS Dn EE | |
| 25 Oct 2024 | FENCING COMPLETED...ONLY PAINTING WORK REMAINING | Thaliparamba WS Dn EE | |
| 23 Oct 2024 | FENCING COMPLETED...ONLY PAINTING WORK REMAINING | Thaliparamba WS Dn EE | |
| 22 Oct 2024 | FENCING COMPLETED...ONLY PAINTING WORK REMAINING | Thaliparamba WS Dn EE | |
| 19 Oct 2024 | Work in progress | Thaliparamba WS Dn EE | |
| 17 Oct 2024 | Work in progress | Thaliparamba WS Dn EE | |
| 17 Oct 2024 | Work in progress | Thaliparamba WS Dn EE | |
| 15 Oct 2024 | Work in progress | Thaliparamba WS Dn EE | |
| 15 Oct 2024 | Work in progress | Thaliparamba WS Dn EE |