14 Dec 2023 | Estimate submitted for approval. | Nattika Project Dn EE | |
08 Dec 2023 | Estimate submitted for approval. | Nattika Project Dn EE | |
04 Dec 2023 | Estimate submitted for approval. | Nattika Project Dn EE | |
30 Nov 2023 | Obtained FS from KIIFB. Estimate submitted for approval. | Nattika Project Dn EE | |
27 Nov 2023 | Obtained FS from KIIFB. Estimate submitted for approval. | Nattika Project Dn EE | |
23 Nov 2023 | Obtained FS from KIIFB. Estimate submitted for approval. | Nattika Project Dn AE 4 | |
15 Nov 2023 | Awaiting for FS from KIIFB. Estimate submitted for approval. | Nattika Project Dn AE 4 | |
09 Nov 2023 | Awaiting for FS from KIIFB. Estimate submitted for approval. | Nattika Project Dn AE 4 | |
02 Nov 2023 | Awaiting for FS from KIIFB. Estimate submitted for approval. | Nattika Project Dn AE 4 | |