| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Nov 2021 | RWPH substation building foundation work completed, WTP tiles fixing work progressing, clarifier plate fixing work progressing, Manjeri office building plastering work progressing | Malappuram Project Dn AE2 | |
| 08 Nov 2021 | WTP - filter media filling completed, elctromechanical work progressing, agitator fixed in flocculator and flash mixer, scraper work in clarifier progressing, tiles and hand rails fixed Manjeri section office building - structural completed, bricks work progressing Cherani sump cum pump house - finishing work progressing Thadaparamba OHSR and Elembra OHS- Finishing work progressing | Malappuram Project Dn AE2 | |
| 05 Nov 2021 | WTP - filter media filling completed, elctromechanical work progressing, agitator fixed in flocculator and flash mixer, scraper work in clarifier progressing, tiles and hand rails fixed Manjeri section office building - structural completed, bricks work progressing Cherani sump cum pump house - finishing work progressing Thadaparamba OHSR and Elembra OHS- Finishing work progressing | Malappuram Project Dn AE2 | |
| 01 Nov 2021 | Bricks work at manjeri office building and electromechanical work at WTP progressing | Malappuram Project Dn AE2 | |
| 25 Oct 2021 | Bricks work at manjeri office building, footing and column work at substation building at RWPH, tile fixing work and electro mechanical work at WTP progressing | Malappuram Project Dn AE2 | |
| 20 Oct 2021 | Bricks work at manjeri office building, electromechanical work at WTP, footing work for sub station building at RWPH are progressing | Malappuram Project Dn AE2 | |
| 11 Oct 2021 | Electromechanical work at WTP, boundary wall at Thadaparamba OHSR, cement plastering work at cherani sump and Manjeri section office Progressing | Malappuram Project Dn AE2 | |
| 27 Sep 2021 | construction work of panel room and shift room at RWPH started | Malappuram Project Dn AE2 | |
| 25 Sep 2021 | Electromechanical work at WTP progressing | Malappuram Project Dn AE2 | |
| 20 Sep 2021 | Electromechanical work at WTP Progressing | Malappuram Project Dn AE2 |