| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 07 Dec 2023 | Estimate under preparation. | Perlassery Sn 2 AE | |
| 25 Nov 2023 | Estimate under preparation. | Perlassery Sn 2 AE | |
| 18 Nov 2023 | Estimate under preparation. | Kannur PH Dn EE | |
| 09 Nov 2023 | AS accorded vide AS No.PIU1/SP/50/2023-24 dated 02.09.2023, estimate under preparation. | Kannur PH Dn EE | |
| 01 Nov 2023 | AS accorded vide AS No.PIU1/SP/50/2023-24 dated 02.09.2023, estimate under preparation. | Perlassery Sn 2 AE | |
| 27 Oct 2023 | AS accorded vide AS No.PIU1/SP/50/2023-24 dated 02.09.2023, estimate under preparation. | Kannur PH Dn EE | |
| 27 Oct 2023 | AS accorded vide AS No.PIU1/SP/50/2023-24 dated 02.09.2023, estimate under preparation. | Kannur PH Dn EE | |
| 19 Oct 2023 | AS accorded vide AS No.PIU1/SP/50/2023-24 dated 02.09.2023, estimate under preparation. | Kannur PH Dn EE | |
| 11 Oct 2023 | AS accorded vide AS No.PIU1/SP/50/2023-24 dated 02.09.2023, estimate under preparation. | Kannur PH Dn EE | |
| 03 Oct 2023 | AS accorded vide AS No.PIU1/SP/50/2023-24 dated 02.09.2023, estimate under preparation. | Perlassery Sn 2 AE |