Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
01 Nov 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
30 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
27 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
24 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
20 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
17 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
14 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
12 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
09 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE | |
07 Oct 2023 | 7424 FHTCs,136.188 Km pipe laying & 2127m GI line installed. Charging and commissioning started on 28.02.2023 | Kollam Project Dn AE |