Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Jan 2024 Pipeline works are ongoing. Kattappana AEE 1
25 Jan 2024 Pipeline works are ongoing. Kattappana AEE 1
24 Jan 2024 Pipeline works are ongoing. Kattappana AEE 1
23 Jan 2024 Pipeline works are ongoing. Kattappana AEE 1
22 Jan 2024 Pipeline works are ongoing. Kattappana AEE 1
20 Jan 2024 So far, laid 1345 meters of 160 mm PVC pipes and 26 meters of 150mm GI pipes. Kattappana AEE 1
19 Jan 2024 So far, laid 1285 meters of 160 mm PVC pipes and 26 meters of 150mm GI pipes. Kattappana AEE 1
16 Jan 2024 So far, laid 982 meters of 160 mm PVC pipes and 26 meters of 150mm GI pipes. Kattappana AEE 1
13 Jan 2024 So far, laid 770 meters of 160 mm PVC pipes and 10 meters of 150mm GI pipes. Kattappana AEE 1
10 Jan 2024 So far, laid 482 meters of 160 mm PVC pipes. Kattappana AEE 1