| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Dec 2022 | Pipe Laying Work in Progress | Painavu PH Section AE | |
| 17 Dec 2022 | Pipe Laying in Progress | Painavu PH Section AE | |
| 13 Dec 2022 | Pipe Laying in Progress | Painavu PH Section AE | |
| 08 Dec 2022 | Work in progress | Painavu PH Section AE | |
| 03 Dec 2022 | Work on going | Painavu PH Section AE | |
| 29 Nov 2022 | Work on going | Painavu PH Section AE | |
| 24 Nov 2022 | Work on going | Painavu PH Section AE | |
| 16 Nov 2022 | Pipe supply done, work started | Painavu PH Section AE | |
| 03 Oct 2022 | pipe not supplied | Painavu PH Section AE | |
| 20 Sep 2022 | Agreement executed, pipe supply not done | Painavu PH Section AE |