Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Jul 2021 | Oorpally area 234 FHTCS provided out of 650FHTCs.Work Order issued for other areas also. | Perlasserry Sn 1 | |
08 Jul 2021 | Oorpally area 234 FHTCS provided out of 650FHTCs.Work Order issued for other areas also. | Perlasserry Sn 1 | |
05 Jul 2021 | Oorpally area 234 FHTCS provided out of 650FHTCs. | Perlasserry Sn 1 | |
02 Jul 2021 | Oorpally area 234 FHTCS provided out of 650FHTCs. | Perlasserry Sn 1 | |
02 Jul 2021 | Oorpally area 150 FHTCS provided out of 650FHTCs. | Kannur PH Dn EE | |
20 Jun 2021 | Oorpally area 134 FHTCS provided out of 650FHTCs.Work Order issued for other areas also. | Perlasserry Sn 1 | |
05 Jun 2021 | Oorpally area 134 FHTCS provided out of 650FHTCs.Work Order issued for other areas also. | Perlasserry Sn 1 | |
22 May 2021 | Oorpally 650FHTCs work started.2923FHTCs tender opening date24/4/21and108 FHTCs provided through quotations.Balance estimate submitted | Perlasserry Sn 1 | |
26 Apr 2021 | Oorpally 650FHTCs work started.2923FHTCs tender opening date24/4/21and108 FHTCs provided through quotations Balance combined estimate submitted | Perlasserry Sn 1 | |
22 Apr 2021 | Oorpally 650FHTCs Agreement executed.2923FHTCs tender opening date24/4/21and108 FHTCs provided through quotations Balance combined estimate submitted | Perlasserry Sn 1 |