Status Date Overall Project Status Project Officer Contact
02 Dec 2021 App developed. Testing in progress. Kuriathy Sewerage Sn2 AE
01 Dec 2021 App developed. Testing in progress. Kuriathy Sewerage Sn2 AE
28 Nov 2021 App developed. Testing in progress. Kuriathy Sewerage Sn2 AE
21 Nov 2021 70% completed. Mobile application development completed. First installment of Rs3.5 Lakhs payment was released to KSREC. The second installment of Rs. 2.8 lakhs is requested by KSREC. DBA has been addressed to share the server details of KWA. Work to be arranged for mapping the network using the App. Kuriathy Sewerage Sn2 AE
18 Nov 2021 70% completed. Mobile application development completed. First installment of Rs3.5 Lakhs payment was released to KSREC. The second installment of Rs. 2.8 lakhs is requested by KSREC. DBA has been addressed to share the server details of KWA. Work to be arranged for mapping the network using the App. Kuriathy Sewerage Sn2 AE
15 Nov 2021 70% completed. Mobile application development completed. First installment of Rs3.5 Lakhs payment was released to KSREC. The second installment of Rs. 2.8 lakhs is requested by KSREC. DBA has been addressed to share the server details of KWA. Work to be arranged for mapping the network using the App. Kuriathy Sewerage Sn2 AE
11 Nov 2021 70% completed. Mobile application development completed. First installment of Rs3.5 Lakhs payment was released to KSREC. The second installment of Rs. 2.8 lakhs is requested by KSREC. DBA has been addressed to share the server details of KWA. Work to be arranged for mapping the network using the App. Kuriathy Sewerage Sn2 AE
08 Nov 2021 70% completed. Mobile application development completed. First installment of Rs3.5 Lakhs payment was released to KSREC. The second installment of Rs. 2.8 lakhs is requested by KSREC. DBA has been addressed to share the server details of KWA. Work to be arranged for mapping the network using the App. Kuriathy Sewerage Sn2 AE
05 Nov 2021 70% completed. Mobile application development completed. First installment of Rs3.5 Lakhs payment was released to KSREC. The second installment of Rs. 2.8 lakhs is requested by KSREC. DBA has been addressed to share the server details of KWA. Work to be arranged for mapping the network using the App. Kuriathy Sewerage Sn2 AE
02 Nov 2021 70% completed. Mobile application development completed. First installment of Rs3.5 Lakhs payment was released to KSREC. The second installment of Rs. 2.8 lakhs is requested by KSREC. DBA has been addressed to share the server details of KWA. Work to be arranged for mapping the network using the App. Kuriathy Sewerage Sn2 AE