| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Jan 2023 | 75% of Pipe laying Completed | Painavu PH Section AE | |
| 04 Jan 2023 | Pipe laying work is going on | Painavu PH Section AE | |
| 26 Dec 2022 | Pipe Laying Works in Progress | Painavu PH Section AE | |
| 17 Dec 2022 | Pipe Laying in Progress | Painavu PH Section AE | |
| 13 Dec 2022 | Pipe Laying Works in Progress | Painavu PH Section AE | |
| 08 Dec 2022 | Work in progress | Painavu PH Section AE | |
| 03 Dec 2022 | Work on going | Painavu PH Section AE | |
| 29 Nov 2022 | Work on going | Painavu PH Section AE | |
| 24 Nov 2022 | Work on going | Painavu PH Section AE | |
| 24 Nov 2022 | Work on going | Painavu PH Section AE |