04 Nov 2024 860 Nos.844 FHTCs given ,,63 mm PVC Pipe 2500 m Supplied. 75 mm PVC Pipe 3000 m Supplied,65MM GI Pipe 1974mtr Supplied, 50MM GI Pipe 2000mtr Supplied, 63 mm PVC -2413.1 mtr laid, 75mm PVC Pipe 1652.5m laid,50mm GI Pipe 1651.8m laid, 65mm GI Pipe 1200.9m Thodupuzha PH Sn
01 Nov 2024 work started, pipe laying ongoing Thodupuzha PH Sn
26 Oct 2024 work started, pipe laying ongoing Thodupuzha PH Sn
21 Oct 2024 work started, pipe laying ongoing Thodupuzha PH Sn
15 Oct 2024 work started, pipe laying ongoing Thodupuzha PH Sn
15 Oct 2024 Duplication of amruth package-2 Thodupuzha PH Sn
07 Oct 2024 work started, pipe laying ongoing Thodupuzha PH Sn
04 Oct 2024 work started, pipe laying ongoing Thodupuzha PH Sn
01 Oct 2024 work started, pipe laying ongoing Thodupuzha PH Sn
01 Oct 2024 373 nos FHTC Given, 9 km pipe laid out of 10.3km.40mm GI Pipe 3000m supplied.(As per bill - 150 mm GI Pipe-503.10 m ,160 mm PVC -1060.40 m,90 mm PVC pipe-4822.90 m , 80 mm GI Pipe-2744.68 , 40 mm GI Pipe-2328.43 m ) 330 nos bill submitted. Thodupuzha PH Sn