| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Nov 2024 | 860 Nos.844 FHTCs given ,,63 mm PVC Pipe 2500 m Supplied. 75 mm PVC Pipe 3000 m Supplied,65MM GI Pipe 1974mtr Supplied, 50MM GI Pipe 2000mtr Supplied, 63 mm PVC -2413.1 mtr laid, 75mm PVC Pipe 1652.5m laid,50mm GI Pipe 1651.8m laid, 65mm GI Pipe 1200.9m | Thodupuzha PH Sn | |
| 01 Nov 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 26 Oct 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 21 Oct 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 15 Oct 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 15 Oct 2024 | Duplication of amruth package-2 | Thodupuzha PH Sn | |
| 07 Oct 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 04 Oct 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 01 Oct 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 01 Oct 2024 | 373 nos FHTC Given, 9 km pipe laid out of 10.3km.40mm GI Pipe 3000m supplied.(As per bill - 150 mm GI Pipe-503.10 m ,160 mm PVC -1060.40 m,90 mm PVC pipe-4822.90 m , 80 mm GI Pipe-2744.68 , 40 mm GI Pipe-2328.43 m ) 330 nos bill submitted. | Thodupuzha PH Sn |