| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 Mar 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 13 Mar 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 11 Mar 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 06 Mar 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 04 Mar 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 01 Mar 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 28 Feb 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 26 Feb 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 23 Feb 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn | |
| 23 Feb 2024 | work started, pipe laying ongoing | Thodupuzha PH Sn |