| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Mar 2023 | work in progress | Oachira AE | |
| 03 Mar 2023 | work in progress | Oachira AE | |
| 01 Mar 2023 | work in progress | Oachira AE | |
| 27 Feb 2023 | work in progress | Oachira AE | |
| 24 Feb 2023 | work in progress | Oachira AE | |
| 22 Feb 2023 | work in progress | Oachira AE | |
| 20 Feb 2023 | work in progress | Oachira AE | |
| 16 Feb 2023 | work in progress | Oachira AE | |
| 16 Feb 2023 | Supply order issued for pipes,75 mm PVC pipe laying started | Oachira AE | |
| 14 Feb 2023 | Supply order issued for pipes,75 mm PVC pipe laying started | Oachira AE |