| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Mar 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-696 m, FHTC- 98, HTC-14 | Kolachery PH Sn AE | |
| 27 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-696 m, FHTC- 98, HTC-14 | Kolachery PH Sn AE | |
| 24 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-2644.5 m, 140 mm 10 Kg/Cm2-820 m, 110 mm 10 Kg/Cm2- 2374.5 m, 90 mm 10 Kg/Cm2-4785.5 m, 75 mm 10 Kg/Cm2-516 m, FHTC- 95 | Kolachery PH Sn AE | |
| 20 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-1380 m, 110 mm 10 Kg/Cm2- 1032 m, 90 mm 10 Kg/Cm2-2718 m, 75 mm 10 Kg/Cm2-516 m, FHTC-86 | Kolachery PH Sn AE | |
| 14 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-1380 m, 110 mm 10 Kg/Cm2- 1032 m, 90 mm 10 Kg/Cm2-2718 m, 75 mm 10 Kg/Cm2-516 m | Kolachery PH Sn AE | |
| 05 Feb 2025 | Work in progress. 160 mm 10 Kg/Cm2-1194 m, 110 mm 10 Kg/Cm2- 846 m, 90 mm 10 Kg/Cm2-2508 m, 75 mm 10 Kg/Cm2-408 m | Kolachery PH Sn AE | |
| 28 Jan 2025 | Work in progress. 160 mm 10 Kg/Cm2-1194 m, 110 mm 10 Kg/Cm2- 846 m, 90 mm 10 Kg/Cm2-2508 m, 75 mm 10 Kg/Cm2-408 m | Kolachery PH Sn AE | |
| 22 Jan 2025 | Work in progress. 160 mm 10 Kg/Cm2-1194 m, 110 mm 10 Kg/Cm2- 24 m, 90 mm 10 Kg/Cm2-924 m, 75 mm 10 Kg/Cm2-222 m | Kolachery PH Sn AE | |
| 14 Jan 2025 | Work in progress. 160 mm 10 Kg/Cm2-1194 m, 110 mm 10 Kg/Cm2- 24 m, 90 mm 10 Kg/Cm2-924 m, 75 mm 10 Kg/Cm2-222 m | Kolachery PH Sn AE | |
| 08 Jan 2025 | Work in progress. 160 mm 10 Kg/Cm2-756 m, 90 mm 10 Kg/Cm2-258m, 75 mm 10 Kg/Cm2-162 m | Kolachery PH Sn AE |