| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 02 Apr 2024 | Disconnection of unusable street taps 170Nos | Chathannur PH Sn AE | |
| 01 Apr 2024 | Disconnection of unusable street taps 170Nos | Chathannur PH Sn AE | |
| 30 Mar 2024 | Disconnection of unusable street taps 168 Nos | Chathannur PH Sn AE | |
| 27 Mar 2024 | Disconnection of unusable street taps 168 Nos | Chathannur PH Sn AE | |
| 23 Mar 2024 | Disconnection of unusable street taps 153 Nos | Chathannur PH Sn AE | |
| 22 Mar 2024 | Disconnection of unusable street taps 153 Nos | Chathannur PH Sn AE | |
| 21 Mar 2024 | Disconnection of unusable street taps 151 Nos | Chathannur PH Sn AE | |
| 20 Mar 2024 | Disconnection of unusable street taps 149 Nos | Chathannur PH Sn AE | |
| 19 Mar 2024 | Disconnection of unusable street taps 148 Nos | Chathannur PH Sn AE | |
| 18 Mar 2024 | Disconnection of unusable street taps 148 Nos | Chathannur PH Sn AE |