Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
11 Apr 2023 | 15.862km pipe line laid(160mm,110mm &90mm HDPE Pipe and 75mm,63mm&50mm PVC Pipe) | Nattika Project Dn | |
10 Apr 2023 | 15km pipe line laid(160mm,110mm &90mm HDPE Pipe and 75mm,63mm&50mm PVC Pipe) | Nattika Project Dn | |
09 Apr 2023 | Work started and 14km pipe line laid | Nattika Project Dn | |
08 Apr 2023 | Work started and 14km pipe line laid | Nattika Project Dn | |
07 Apr 2023 | Work started and 13.5km pipe line laid | Nattika Project Dn | |
06 Apr 2023 | Work started and 13.5km pipe line laid | Nattika Project Dn | |
05 Apr 2023 | Work started and 12km pipe line laid | Nattika Project Dn | |
04 Apr 2023 | Work started and 12km pipe line laid | Nattika Project Dn | |
03 Apr 2023 | Work started and 11km pipe line laid | Nattika Project Dn | |
02 Apr 2023 | Work started and 11 km pipe line laid | Nattika Project Dn |