| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 May 2025 | Work completed on 11/05/2025. | Oachira AE | |
| 08 May 2025 | Work started on 27/04/2025. Laying of 63 mm PVC pipe (total length 70 m) and interconnection work completed. Re-concreting ongoing. | Oachira AE | |
| 05 May 2025 | Work started on 27/04/2025. Laying of 63 mm PVC pipe (total length 70 m) and interconnection work completed. Re-concreting ongoing. | Oachira AE | |
| 05 May 2025 | Work started on 27/04/2025. Laying of 63 mm PVC pipe- 70 m completed, interconnection work completed and re concreting ongoing. | Oachira AE | |
| 05 May 2025 | Work started on 27/04/2025. Demolishing concrete completed. Pipe laying and interconnection work ongoing. | Oachira AE | |
| 02 May 2025 | Work started on 27/04/2025. Demolishing concrete completed. Pipe laying and interconnection work ongoing. | Oachira AE | |
| 29 Apr 2025 | Work started on 27/04/2025. Demolishing concrete completed. Pipe laying and interconnection work ongoing. | Oachira AE | |
| 28 Apr 2025 | Work started on 27/04/2025. Demolishing concrete completed. Pipe laying and interconnection work ongoing. | Oachira AE | |
| 25 Apr 2025 | Work not started yet. Letter given to the contractor for starting work | Oachira AE | |
| 24 Apr 2025 | Work not started yet. Letter given to the contractor for starting work | Oachira AE |