Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Nov 2023 200 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
20 Nov 2023 200 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
13 Nov 2023 200 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
10 Nov 2023 198 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
06 Nov 2023 196 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
03 Nov 2023 194 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
01 Nov 2023 192 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
30 Oct 2023 192 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
27 Oct 2023 189 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn
25 Oct 2023 187 FHTC given,newly laid line - 40 mm GI Pipe-1000 m,As per bill - 40 mm GI Pipe-811.60 m Thodupuzha PH Sn