| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Jan 2025 | Work in progress. | Edappal PH Dn EE | |
| 17 Dec 2024 | Work in progress. | Edappal PH Dn EE | |
| 22 Nov 2024 | Work in progress. | Edappal PH Dn EE | |
| 11 Nov 2024 | Work in progress. | Edappal PH Dn EE | |
| 05 Nov 2024 | Work in progress. | Edappal PH Dn EE | |
| 21 Oct 2024 | Work in progress | Kottakkal PH Sn AE | |
| 08 Oct 2024 | work in progress | Kottakkal PH Sn AE | |
| 28 Sep 2024 | work in progress | Kottakkal PH Sn AE | |
| 26 Sep 2024 | Work ongoing | Kottakkal PH Sn AE | |
| 07 Sep 2024 | work in progress, but NH and PWD road permission not availed. | Kottakkal PH Sn AE |