| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 26 Sep 2024 | Work started on 03.09.2024. 295 public taps disconnected | Chavara AE | |
| 23 Sep 2024 | Work started on 03.09.2024. 295 public taps disconnected | Chavara AE | |
| 18 Sep 2024 | Work started on 03.09.2024. 273 public taps disconnected | Chavara AE | |
| 10 Sep 2024 | Work started on 03.09.2024. 190 public taps disconnected | Chavara AE | |
| 07 Sep 2024 | Work started on 03.09.2024. 136 public taps disconnected | Chavara AE | |
| 04 Sep 2024 | Work started on 03.09.2024. 81 public taps disconnected | Chavara AE | |
| 02 Sep 2024 | Work order issued | Chavara AE | |
| 30 Aug 2024 | Work order issued | Chavara AE | |
| 24 Aug 2024 | Work order issued | Chavara AE | |
| 21 Aug 2024 | Work order issued | Chavara AE |