Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2022 Work in progress Kumbala PH Sn AE
12 May 2022 Work in progress Kumbala PH Sn AE
10 May 2022 Arikady kadavarth and Kanchikatta area work in progress Kumbala PH Sn AE
06 May 2022 Arikady kadavarth and Kanchikatta area work in progress Kumbala PH Sn AE
02 Mar 2022 Phase II - Part I - Arikady Kadavath pipeline - Pipe line work in progress Kumbala PH Sn AE
26 Feb 2022 Phase II - Part I - Arikady Kadavath pipeline - Pipe line work in progress Kumbala PH Sn AE
21 Feb 2022 Phase II - Part I - Arikady Kadavath pipeline - Pipe line work in progress Kumbala PH Sn AE
18 Feb 2022 Phase II - Part I - Arikady Kadavath pipeline - Pipe line work in progress Kumbala PH Sn AE
14 Feb 2022 Phase II - Part I - Arikady Kadavath pipeline - Pipe line work in progress Kumbala PH Sn AE
18 Dec 2021 completed on 15/12/2021 Kumbala PH Sn AE