| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Jun 2023 | E Bill submitted | Kollam WS Sn 2 - AE | |
| 12 Jun 2023 | completed | Kollam WS Sn 2 - AE | |
| 09 Jun 2023 | Work completed | Kollam WS Sn 2 - AE | |
| 06 Jun 2023 | Work completed | Kollam WS Sn 2 - AE | |
| 05 Jun 2023 | Work started on 3/6/23 and in progress | Kollam WS Sn 2 - AE | |
| 01 Jun 2023 | Contractor informed that tested pipe will reach the site on today . | Kollam WS Sn 2 - AE | |
| 29 May 2023 | Site handed over, waiting for tested pipe | Kollam WS Sn 2 - AE | |
| 24 May 2023 | Site handed over, waiting for tested pipe | Kollam WS Sn 2 - AE | |
| 22 May 2023 | Site handed over, waiting for tested pipe | Kollam WS Sn 2 - AE | |