| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Mar 2023 | Work started and 6 km pipe line laid | Nattika Project Dn | |
| 17 Mar 2023 | Work started and 6 km pipe line laid | Nattika Project Dn | |
| 16 Mar 2023 | Work started and 6 km pipe line laid | Nattika Project Dn | |
| 15 Mar 2023 | Work started and 5 km pipe line laid | Nattika Project Dn | |
| 14 Mar 2023 | Work started and 5 km pipe line laid | Nattika Project Dn | |
| 13 Mar 2023 | Work started and 5 km pipe line laid | Nattika Project Dn | |
| 12 Mar 2023 | Work started and 5 km pipe line laid | Nattika Project Dn | |
| 11 Mar 2023 | Work started and 5 km pipe line laid | Nattika Project Dn | |
| 10 Mar 2023 | Work started and 5 km pipe line laid | Nattika Project Dn | |