Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Jul 2021 | 53% completed | Neyyattinkara WS Dn EE | |
17 Jul 2021 | 53% completed | Neyyattinkara WS Dn EE | |
16 Jul 2021 | 53% completed | Neyyattinkara WS Dn EE | |
12 Jul 2021 | 51% completed | Neyyattinkara WS Dn EE | |
09 Jul 2021 | 51% completed. | Neyyattinkara WS Dn EE | |
02 Jul 2021 | 45% completed. | Neyyattinkara WS Dn EE | |
02 Jul 2021 | 42% completed. | Neyyattinkara WS Dn EE | |
28 Jun 2021 | 42% completed. | Neyyattinkara WS Dn EE | |
22 Jun 2021 | 42% completed. | Neyyattinkara WS Dn EE | |
21 Jun 2021 | 42% completed | Neyyattinkara WS Dn EE |