Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Mar 2022 | Total geotagged connections 6965 | Kollam Project Dn AE | |
25 Mar 2022 | Total geotagged connections 6965 | Kollam Project Dn AE | |
24 Mar 2022 | Total geotagged connections 6965 | Kollam Project HD | |
22 Mar 2022 | Total geotagged connections 6775 | Kollam Project Dn AE | |
21 Mar 2022 | Total geotagged connections 6775 | Kollam Project Dn AE | |
19 Mar 2022 | Total geotagged connections 6775 | Kollam Project Dn AE3 | |
18 Mar 2022 | Total geotagged connections 6775 | Kollam Project Dn AE | |
17 Mar 2022 | Total geotagged connections 6775 | Kollam Project Dn AE | |
16 Mar 2022 | Total geotagged connections 6775 | Kollam Project Dn AE | |
14 Mar 2022 | Total geotagged connections 6775 | Kollam Project Dn AE |