| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 10 Feb 2023 | work order issued | Perlassery Sn 2 AE | |
| 09 Feb 2023 | work order issued | Perlassery Sn 2 AE | |
| 02 Feb 2023 | work order issued | Perlassery Sn 2 AE | |
| 29 Jan 2023 | Work order issued | Perlassery Sn 2 AE | |
| 20 Jan 2023 | Work order issued | Perlassery Sn 2 AE | |
| 07 Jan 2023 | Submitted to SE for tender sanction | Perlassery Sn 2 AE | |
| 04 Jan 2023 | Submitted to SE for tender sanction | Perlassery Sn 2 AE | |
| 30 Dec 2022 | Submitted to SE for tender sanction | Perlassery Sn 2 AE | |
| 26 Dec 2022 | Submitted to SE for tender sanction | Perlassery Sn 2 AE | |
| 21 Dec 2022 | Work tendered. Single response received.Tender due date extended. | Perlassery Sn 2 AE |