| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Mar 2026 | 143700 m pipe laid 395 HTC and 1844 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 28 Feb 2026 | 143700 m pipe laid 395 HTC and 1844 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 23 Feb 2026 | 143700 m pipe laid 395 HTC and 1844 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 19 Feb 2026 | 143700 m pipe laid 395 HTC and 1844 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 13 Feb 2026 | 143700 m pipe laid 383 HTC and 1764 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 07 Feb 2026 | 143700 m pipe laid 383 HTC and 1764 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 02 Feb 2026 | 143700 m pipe laid 383 HTC and 1764 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 27 Jan 2026 | 143700 m pipe laid 383 HTC and 1764 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 21 Jan 2026 | 143700 m pipe laid 403 HTC and 1689 FHTC given , Work in progress . | Koothuparamba Proj AE 2 | |
| 17 Jan 2026 | 143700 m pipe laid 403 HTC and 1689 FHTC given , Work in progress . | Koothuparamba Proj AE 2 |