Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Vandoor AE
Date: 16/03/2025

Work has been completed | 100% Completed

Work completed-(PIPE LAID- 90 mm PVC 8kg/cm2 -7KM , 80mm GI PIPE -1.5 KM ,FHTC - 1250/1250 NOS) FINAL BILL SUBMITTED ON 15/03/2025

Vandoor AE
Date: 11/03/2025

Work in progress | 99% Completed

PIPE LAID - 7KM FHTC - 1250/1480 NOS

Vandoor AE
Date: 20/01/2025

Work in progress | 90% Completed

PIPE LAID - 7KM FHTC - 1233/1480 NOS

Vandoor AE
Date: 17/01/2025

Work in progress | 90% Completed

PIPE LAID - 7KM FHTC - 1233/1480 NOS

Vandoor AE
Date: 15/01/2025

Work in progress | 90% Completed

PIPE LAID - 7KM FHTC - 1233/1480 NOS

Vandoor AE
Date: 09/01/2025

Work in progress | 90% Completed

PIPE LAID - 7KM FHTC - 1233/1480 NOS

Vandoor AE
Date: 01/01/2025

Work in progress | 75% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work completed, plumbing work of office building is completed.

Vandoor AE
Date: 26/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.

Vandoor AE
Date: 24/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.

Vandoor AE
Date: 20/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.

Vandoor AE
Date: 18/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.

Vandoor AE
Date: 13/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed, Floor work and plumbing work of office building is progressing.

Vandoor AE
Date: 12/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 09/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 06/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 04/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 02/12/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 29/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 27/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 25/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 22/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 20/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 18/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 15/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 11/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 07/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building is completed.

Vandoor AE
Date: 05/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.

Vandoor AE
Date: 02/11/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.

Vandoor AE
Date: 29/10/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.

Vandoor AE
Date: 24/10/2024

Work in progress | 50% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.

Vandoor AE
Date: 22/10/2024

Work in progress | 1% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.

Vandoor AE
Date: 18/10/2024

Work in progress | 1% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.

Vandoor AE
Date: 16/10/2024

Work in progress | 1% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.

Vandoor AE
Date: 14/10/2024

Work in progress | 1% Completed

1200 connection shifting, Plastering of office building is completed, Road work of office building in progress.

Malappuram PH Dn EE
Date: 10/01/2024

Work has started | 0% Completed

TS Issued on 10.01.2024