Kochi PH Dn EE |
Date: 03/07/2022 |
Work has been completed | 100% Completed
work complete d
Kochi PH Dn EE |
Date: 01/07/2022 |
Work has been completed | 100% Completed
work completed
Kochi PH Dn EE |
Date: 01/06/2022 |
Work has been completed | 100% Completed
work completed
Kochi PH Dn EE |
Date: 09/05/2022 |
Work has been completed | 100% Completed
Work has been completed, 100%
Kochi PH Dn EE |
Date: 23/04/2022 |
Work has been completed | 100% Completed
Work has been completed, 100%
Kochi PH Dn EE |
Date: 07/03/2022 |
Work has been completed | 100% Completed
Work has been completed 100% Completed
Kochi PH Dn EE |
Date: 20/02/2022 |
Work has been completed | 100% Completed
Work has been completed , 100% Completed
Kochi PH Dn EE |
Date: 13/02/2022 |
Work has been completed | 100% Completed
work complete d
Kochi PH Dn EE |
Date: 28/01/2022 |
Work has been completed | 100% Completed
work completed
Kochi PH Dn EE |
Date: 18/01/2022 |
Work has been completed | 100% Completed
work completed
Kochi PH Dn EE |
Date: 03/01/2022 |
Work has been completed | 100% Completed
work completed
Kochi PH Dn EE |
Date: 21/12/2021 |
Work has been completed | 100% Completed
work completed
Kochi PH Dn EE |
Date: 17/12/2021 |
Work has been completed | 100% Completed
Work has been completed
Kochi PH Dn EE |
Date: 14/12/2021 |
Work has been completed | 100% Completed
Work has been completed |
Kochi PH Dn EE |
Date: 20/04/2021 |
Work has been completed | 100% Completed
Bill amount paid to contractor
Kochi PH Dn EE |
Date: 15/04/2021 |
Work has been completed | 100% Completed
Bill submitted
Kochi PH Dn EE |
Date: 15/03/2021 |
Work has been completed | 100% Completed
Bill under preparation
Kochi PH Dn EE |
Date: 09/03/2021 |
Work has been completed | 100% Completed
Work completed.Total 392 nos completed.
Kochi PH Dn EE |
Date: 05/03/2021 |
Work in progress | 90% Completed
Domestic 339 Nos & Non Domestic 51 Nos
Kochi PH Dn EE |
Date: 27/02/2021 |
Work in progress | 84% Completed
Domestic 319 Nos & Non Domestic 45 Nos completed
Kochi PH Dn EE |
Date: 24/02/2021 |
Work in progress | 80% Completed
Domestic 307 Nos & Non Domestic 44 Nos
Kochi PH Dn EE |
Date: 23/02/2021 |
Work in progress | 75% Completed
Domestic 283 Nos & Non Domestic 41 Nos completed
Kochi PH Dn EE |
Date: 18/02/2021 |
Work in progress | 70% Completed
Domestic 268 Nos & Non domestic - 40 Nos Completed
Kochi PH Dn EE |
Date: 17/02/2021 |
Work in progress | 70% Completed
296nos completed
Kochi PH Dn EE |
Date: 10/02/2021 |
Work in progress | 57% Completed
262nos completed
Kochi PH Dn EE |
Date: 06/02/2021 |
Work in progress | 55% Completed
231nos completed
Kochi PH Dn EE |
Date: 03/02/2021 |
Work in progress | 35% Completed
188 nos compleated
Kochi PH Dn EE |
Date: 01/02/2021 |
Work in progress | 25% Completed
149nos completed
Kochi PH Dn EE |
Date: 27/01/2021 |
Work in progress | 23% Completed
135 connections were compleated
Kochi PH Dn EE |
Date: 23/01/2021 |
Work in progress | 20% Completed
114 connection completed
Kochi PH Dn EE |
Date: 29/11/2020 |
Work has started | 0% Completed
Tendered with due date 23/01/2020,.Further extended to 27/01/2020.No body participated.Retendered with due date 12/02/2020. Extended up to 19/02/2020,24/02/2020 and . 03/03/2020.Nobody participated.Retendered with due date 17/10/2020.Nobody participated. Extended to 23/10/2020,12/11/2020, 18/11/2020,25/11/2020,03/12/2020.