Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

All updates

Kochi PH Dn EE
Date: 03/07/2022

Work has been completed | 100% Completed

work complete d

Kochi PH Dn EE
Date: 01/07/2022

Work has been completed | 100% Completed

work completed

Kochi PH Dn EE
Date: 01/06/2022

Work has been completed | 100% Completed

work completed

Kochi PH Dn EE
Date: 09/05/2022

Work has been completed | 100% Completed

Work has been completed, 100%

Kochi PH Dn EE
Date: 23/04/2022

Work has been completed | 100% Completed

Work has been completed, 100%

Kochi PH Dn EE
Date: 07/03/2022

Work has been completed | 100% Completed

Work has been completed 100% Completed

Kochi PH Dn EE
Date: 20/02/2022

Work has been completed | 100% Completed

Work has been completed , 100% Completed

Kochi PH Dn EE
Date: 13/02/2022

Work has been completed | 100% Completed

work complete d

Kochi PH Dn EE
Date: 28/01/2022

Work has been completed | 100% Completed

work completed

Kochi PH Dn EE
Date: 18/01/2022

Work has been completed | 100% Completed

work completed

Kochi PH Dn EE
Date: 03/01/2022

Work has been completed | 100% Completed

work completed

Kochi PH Dn EE
Date: 21/12/2021

Work has been completed | 100% Completed

work completed

Kochi PH Dn EE
Date: 17/12/2021

Work has been completed | 100% Completed

Work has been completed

Kochi PH Dn EE
Date: 14/12/2021

Work has been completed | 100% Completed

Work has been completed |

Kochi PH Dn EE
Date: 20/04/2021

Work has been completed | 100% Completed

Bill amount paid to contractor

Kochi PH Dn EE
Date: 15/04/2021

Work has been completed | 100% Completed

Bill submitted

Kochi PH Dn EE
Date: 15/03/2021

Work has been completed | 100% Completed

Bill under preparation

Kochi PH Dn EE
Date: 09/03/2021

Work has been completed | 100% Completed

Work completed.Total 392 nos completed.

Kochi PH Dn EE
Date: 05/03/2021

Work in progress | 90% Completed

Domestic 339 Nos & Non Domestic 51 Nos

Kochi PH Dn EE
Date: 27/02/2021

Work in progress | 84% Completed

Domestic 319 Nos & Non Domestic 45 Nos completed

Kochi PH Dn EE
Date: 24/02/2021

Work in progress | 80% Completed

Domestic 307 Nos & Non Domestic 44 Nos

Kochi PH Dn EE
Date: 23/02/2021

Work in progress | 75% Completed

Domestic 283 Nos & Non Domestic 41 Nos completed

Kochi PH Dn EE
Date: 18/02/2021

Work in progress | 70% Completed

Domestic 268 Nos & Non domestic - 40 Nos Completed

Kochi PH Dn EE
Date: 17/02/2021

Work in progress | 70% Completed

296nos completed

Kochi PH Dn EE
Date: 10/02/2021

Work in progress | 57% Completed

262nos completed

Kochi PH Dn EE
Date: 06/02/2021

Work in progress | 55% Completed

231nos completed

Kochi PH Dn EE
Date: 03/02/2021

Work in progress | 35% Completed

188 nos compleated

Kochi PH Dn EE
Date: 01/02/2021

Work in progress | 25% Completed

149nos completed

Kochi PH Dn EE
Date: 27/01/2021

Work in progress | 23% Completed

135 connections were compleated

Kochi PH Dn EE
Date: 23/01/2021

Work in progress | 20% Completed

114 connection completed

Kochi PH Dn EE
Date: 29/11/2020

Work has started | 0% Completed

Tendered with due date 23/01/2020,.Further extended to 27/01/2020.No body participated.Retendered with due date 12/02/2020. Extended up to 19/02/2020,24/02/2020 and . 03/03/2020.Nobody participated.Retendered with due date 17/10/2020.Nobody participated. Extended to 23/10/2020,12/11/2020, 18/11/2020,25/11/2020,03/12/2020.