Chavasseryparamba HW AE |
Date: 20/01/2023 |
Work has been completed | 100% Completed
Bill submitted
Kannur WS Sub-Dn - AEE |
Date: 13/01/2023 |
Work has been completed | 100% Completed
Work completed.
Kannur WS Sn AE 2 |
Date: 21/12/2022 |
Work in progress | 60% Completed
Work in progress
Kannur WS Sn AE 2 |
Date: 19/12/2022 |
Work in progress | 60% Completed
Work in progress
Kannur WS Sn AE 2 |
Date: 15/12/2022 |
Work in progress | 5% Completed
Work in progress
Kannur WS Sn AE 2 |
Date: 12/12/2022 |
Work in progress | 5% Completed
Work in progress
Kannur WS Sn AE 2 |
Date: 09/12/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 06/12/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 03/12/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 30/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 26/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 23/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 19/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 16/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 14/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 10/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 05/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 03/11/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 31/10/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 29/10/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 27/10/2022 |
Work in progress | 5% Completed
Work started
Kannur WS Sn AE 2 |
Date: 28/09/2022 |
Work has started | 0% Completed
Work not started.
Kannur WS Sn AE 2 |
Date: 26/09/2022 |
Work has started | 0% Completed
Work order issued. Work not started.